ANALISA EFFISIENSI PLTU PAITON KETIKA HIGH PRESSURE HEATER (HPH 7) INSERVICE DAN OUTSERVICE ANALISA EFFISIENSI PLTU PAITON KETIKA HIGH PRESSURE HEATER (HPH 7) INSERVICE DAN OUTSERVICE

Main Article Content

Sigit Untoro Nova Risdiyanto Ismail Akhmad Farid Purbo Suwandono

Abstract

National electricity needs are always increasing, for that the efficiency of power plants needs to be maintained and expected to be improved. To maintain the efficiency of the power plant, it is necessary to feed water system as a provider of feed water before entering the boiler in good condition and one of the equipment is the High Pressure Heater (HPH). In Paiton Power Plant there are HPH numbers 5.6 and 7. This research aims to compare the efficiency of power plants and the losses caused when pltu operates in hph 7 inservice and outservice conditions. The research method used is a simulation in the simulator room of PLTU PT. PJB UP Paiton 1 & 2.  From the data obtained then done calculations. Research produces the efficiency value of PLTU when in HPH 7 inservice condition is 33.40% and when outservice is 29.20%. The need for coal to increase the temperature lost due to HPH 7 outservice amounted to 11.11 Tons / hour, so that the losses caused by the increase in coal flow amounted to Rp 1,204.896.000 per year.

Downloads

Download data is not yet available.

Article Details

How to Cite
Untoro, S., Ismail, N., Farid, A., & Suwandono, P. (2022). ANALISA EFFISIENSI PLTU PAITON KETIKA HIGH PRESSURE HEATER (HPH 7) INSERVICE DAN OUTSERVICE. Jurnal Energi Dan Teknologi Manufaktur (JETM), 5(01), 07-12. https://doi.org/https://doi.org/10.33795/jetm.v5i01.113
Section
Articles

References

[1] B. Mokalu and C. J. Paat, “Dampak Pembangunan PLTU Terhadap Perubahan Mata Pencarian Masyarakat Desa Binjeita II Kecamatan Bolangitang Timur Kabupaten Bolaang Mongondow Provinsi Sulawesi Utara,” J. Ilm. Soc., vol. 1, no. 1, pp. 1–8, 2021.
[2] P. T. Listrik, “Rencana usaha penyediaan tenaga listrik (ruptl) pt pln (persero).”
[3] C. Wiharya, “Kajian optimasi Unit Jasa Pembangkitan Pembangkit Listrik Tenaga Uap ( UJP PLTU ) Indonesia Power,” vol. 18, no. 2, pp. 18–29, 2020.
[4] Cahyadi, “KAJIAN TEKNIS PEMBANGKIT LISTRIK BERBAHAN BAKAR FOSSIL,” JITE, vol. 1, no. 12, pp. 21–32, 2011.
[5] W. D. S. and Dkk, “Analisis Perhitungan Efisiensi Boiler Kapasitas 55 Ton / Jam di PT PT . PJB ( Pembangkit Jawa Bali ) PLTU Ketapang 2X10 MW,” J. Tekini, vol. 1, no. 2, pp. 3–7, 2017.
[6] A. N. Ristyanto, J. Windarto, and S. Handoko, “SIMULATOR EFISIENSI SISTEM PEMBANGKIT LISTRIK TENAGA UAP,” TRANSIENT, vol. 2, no. 2, pp. 234–240, 2013.
[7] PT. PLN, Thermodinamika Diklat Pengoperasian Alat Bantu PLTU (Modul 3/op). PT. PLN Unit Pendidikan Dan Pelatiahan Suralaya, 2004.
[8] M. U. Damayanti and B. U. K. Widodo, “Analisis Termal High Pressure Feedwater Heater di PLTU PT. XYZ,” J. Tek. ITS, vol. 5, no. 2, pp. 569–574, 2016.
[9] I. Putra, “Studi perhitungan heat exchanger type shell and tube dehumidifier biogas limbah sawit untuk pembangkit listrik tenaga biogas,” J. POLIMESIN, vol. 15, no. 2, pp. 42–49, 2017.
[10] PJB-IMS, Instruksi Kerja (IK) Cold Start.UP Paiton. 2019.
[11] S. S. Hamon, Paiton Steam Power Plant 1&2 Tokyo-Japan. sumitomo corporation, 1990.
[12] W. T. Kurnia, Analisa Efisiensi Mesin Boiler Pada Unit 2 PT. Pembangkitan Jawa Bali Up Paiton Dengan Metode Asme Ptc 4.1. Laporan Kerja Praktek PT. Pembangkitan Jawa Bali UP Paiton, 2019.
[13] Y. V Proskurin, “Analysis of Boiler Engine Efficiency Unit 2 PT . PJB UP Paiton Analysis of Boiler Engine Efficiency Unit 2 PT . PJB UP Paiton,” 2021.
[14] A. N. ABRARI, Analisis efisiensi boiler sebelum dan sesudah overhaul di pltu suralaya unit 8 skripsi. PROGRAM STRATA SATU FAKULTAS TEKNOLOGI DAN BISNIS ENERGI INSTITUT TEKNOLOGI PLN, 2020.
[15] I. Febianto, M. I. Arsyad, and G. S. Lubis, “STUDI EFISIENSI THERMAL BOILER MENGGUNAKAN DIRECT METHOD PADA PLTU SUNGAI RINGIN DI KABUPATEN SINTANG Indra Febianto 1) , M.,” 2017.
[16] Pusat Pendidikan dan Pelatihan, Efisiensi. PT. PLN (Persero).